99-09-21
0730 To CANMET and continued
work on the AES process with the wires. . . .
.
At about 1730 hrs, Jim FOOT, Gus SIDLA, Christopher FUELLEMANN
had a discussion over the future of the beads that I joined in
on. It was started by Christopher at this
time as he will be leaving tomorrow for Shearwater.
He is concerned that the Auger process is not working
effectively and that another process should be looked for.
He is concerned that BROWN is looking too closely at
things that are not in the mandate and thus causing delays.
He is quite adamant that this should be done and implied
that it should be done soon. Jim FOOT
explained that Dr. BROWN would have to look at the remainder of
the Seattle wires before he can come up with suitable test
results and that this will take time. He also
explained that AUGER is the best process for the job at hand,
that there is really nothing else to be used which is
non-destructive. Certainly, anything else
will certainly be destructive, as the bead will have to be
sliced. Indeed, other processes have been
tried along these lines on other test wires and they failed
miserably. I suggested that we should
continue with the Auger and that it will make use of the time
until all of the material is off the bottom.
It must be remembered that further wires may appear.
By then either the Auger process will prove to work or
something else can be looked at knowing that there is nothing
left to come off the ocean floor. Both Jim
FOOT & Gus SIDLA stated that nothing destructive would be done
until a much later date. Gus advised that it
was their intention to do scanning electron microscopic (SEM)
photography of the beads, but it is unknown now if they will be
cut. It will require quite a sophisticated
process in order to cut the beads. It may be
noted that Larry FOGG has expressed his own doubts about AES and
has likely been talking with Christopher. It
was stated that SWISSAIR is applying pressure to Christopher to
come up with answers (likely the same with Boeing for FOGG &
BERRY). It may be noted that Larry FOGG has
been watching the whole process very closely taking extensive
notes and whenever he sees something strange, he is the first to
request clarification. Just as in Seattle he
is the one who is causing many of the delays, not intentionally,
but merely to ensure something was done correctly or to verify
something. Jim FOOT advised Christopher that
there was not a time limit on this process, and if they were
attending in the hopes that things would be done speedily then
they were in the wrong place. It is obvious
that Jim FOOT feels that if millions can be spent to bring
debris off the ocean floor then he can spend several tens of
thousands to try and come up with an answer.
At 2030 hrs, finished and everything locked up.
(Clarification:)
I found the position taken by Jim Foot to be
somewhat strange.
Throughout, he had been adamant that the cause of the fire was a
short-circuited wire, and the sooner this was determined, the
better. However, now he wants to take his time. Jim
Foot operated to his own agenda and time schedule, so he had his
own ulterior motives behind all of this. But for Swissair
to be in such a hurry was just as puzzling. Perhaps too
they had their agenda.